Facts
- Davis Contractors Ltd entered into a contract with Fareham Urban District Council to construct 78 houses at a fixed price, with an estimated completion in eight months.
- The project encountered unforeseen shortages of labour and materials, resulting in significant delays and increased costs.
- Completion was extended to 22 months due to these difficulties.
- The contractors argued the contract was frustrated by the unforeseen delays and rising expenses, seeking extra payment on a quantum meruit basis, asserting the original contract was no longer binding.
- The local authority maintained that the contract should be performed according to its agreed terms.
Issues
- Whether the increased difficulty, delay, and cost due to labour and material shortages constituted frustration of contract.
- Whether the contractors were entitled to extra payment beyond the fixed price on the basis that the contract was frustrated.
- Whether the doctrine of frustration should be applied using the implied term theory or a construction-based approach to the contract.
Decision
- The House of Lords rejected the contractors’ claim of frustration, holding that the delays and increased costs did not amount to a fundamental change in the contractual obligation.
- The contract’s core remained the construction of the houses; the performance, though more onerous, was not radically different from the parties’ original intention.
- The court confirmed that frustration requires an event to render contractual obligations fundamentally different, not simply more difficult or expensive.
- The House of Lords moved away from the implied term theory, endorsing a construction-based approach to determining frustration.
- The claim for additional payment failed, and the original contract remained enforceable.
Legal Principles
- Frustration requires a radical change in the nature of contractual obligations; mere hardship, delay, or expense is insufficient.
- The doctrine operates by law, not on hypothetical intentions of the parties.
- The test for frustration involves an objective analysis of whether the contract is capable of applying to the new circumstances, not what the parties might have agreed.
- If difficulties or delays were foreseeable, frustration will generally not apply; parties are expected to allocate such risks contractually.
- The implied term theory is rejected; courts must construe the contract and circumstances to determine frustration.
Conclusion
Davis Contractors Ltd v Fareham UDC established that only a fundamental, unforeseen change transforming the nature of contractual obligations amounts to frustration. Increased difficulty or cost does not suffice, and the courts apply an objective, construction-based approach to decide such claims. The principles from this case define the narrow boundaries for applying the doctrine of frustration in English contract law.