Facts
- Mr. Hoenig contracted with Mr. Isaacs to redecorate a one-room flat for a lump sum of £750.
- On completion, Mr. Isaacs refused to pay the £350 balance, citing defects in the bookcase and wardrobe.
- The cost to remedy these defects was estimated at £55.
- Mr. Isaacs contended that because the work did not meet precise contractual specifications, no payment was due.
- The court was asked to decide whether Mr. Hoenig was entitled to any payment given the existence of these defects.
Issues
- Whether complete and perfect performance was a condition precedent to Mr. Hoenig’s right to payment under the contract.
- Whether substantial performance had been achieved, entitling Mr. Hoenig to the contract price minus deductions for defects.
- To what extent minor breaches or defects affect payment obligations in lump sum contracts for work and labour.
Decision
- The Court of Appeal held that the contract did not require perfect, error-free completion before payment could be demanded.
- Mr. Hoenig was entitled to the contract price less the cost of remedying the defects.
- The court distinguished between a breach that amounted to total non-performance and minor defects, ruling that only the former could defeat a contractor's right to payment.
- The appeal by Mr. Isaacs was dismissed.
Legal Principles
- Substantial performance in a contract for work and labour entitles the party to payment, subject to deduction for any defects.
- Not all breaches necessitate complete withholding of payment; only those going to the root of the contract allow the other party to refuse payment outright.
- Conditions precedent must be fully satisfied to trigger obligations, but completion clauses in work contracts are usually construed as terms, not strict conditions.
- The substance of the contract, rather than minor deviations, determines entitlement to payment.
- Earlier case law, such as Cutter v Powell, was inapplicable to situations involving minor defects rather than fundamental non-performance.
- Quantum meruit, or payment for partial work, is not generally available unless substantial performance is achieved or a new contract may be inferred, as distinguished in Sumpter v Hedges.
Conclusion
Hoenig v Isaacs confirmed that substantial performance is sufficient for claiming payment under lump sum work contracts, subject to deductions for defects. Minor imperfections do not justify complete withholding of payment; only fundamental failures do. This decision represents a departure from stricter earlier interpretations and clarifies the distinction between conditions and terms within contract law.