Learning Outcomes
This article explains liquidated damages, penalties, and contractual limitations of remedies, including:
- How to distinguish an enforceable liquidated damages clause from an unenforceable penalty by applying the common-law “uncertainty” and “reasonable forecast” requirements to typical MBE-style fact patterns.
- How courts under both common law and UCC §2-718 assess reasonableness, including the role of anticipated versus actual damages, and how that timing difference is tested on the exam.
- How to analyze mixed provisions that contain both valid liquidated damages and clearly penal amounts, and how severability affects the remedies a bar-exam answer should recognize.
- How contractual limitations of remedies—such as exclusive repair-or-replace terms, damages caps, and exclusions of consequential damages—operate in practice and interact with the doctrine of “failure of essential purpose” under UCC §2-719.
- How to evaluate exclusions of consequential damages for commercial loss versus personal injury in consumer-goods transactions, with particular attention to when a clause is prima facie unconscionable.
- How unconscionability can invalidate an agreed damages clause or limitation of remedies, and how to structure an exam answer that clearly separates penalty analysis, failure-of-essential-purpose analysis, and unconscionability analysis.
MBE Syllabus
For the MBE, you are required to understand agreed damages provisions and contractual limitations on remedies, with a focus on the following syllabus points:
- Requirements for an enforceable liquidated damages clause.
- Distinguishing liquidated damages from penalties.
- Consequences of an unenforceable penalty clause.
- Contractual limitation of remedies at common law and under UCC Article 2.
- Unconscionability and “failure of essential purpose” in limiting remedies.
- Special UCC rules on excluding consequential damages for personal injury in consumer goods.
Test Your Knowledge
Attempt these questions before reading this article. If you find some difficult or cannot remember the answers, remember to look more closely at that area during your revision.
-
Which of the following is most likely to make a liquidated damages clause unenforceable?
- The damages are difficult to estimate at contract formation.
- The amount is a reasonable forecast of anticipated harm.
- The clause is intended to punish breach rather than compensate loss.
- The clause applies only if the breach is willful.
-
Under the UCC, a contractual limitation on consequential damages for personal injury in consumer goods is:
- Always enforceable.
- Enforceable unless the limitation is unconscionable.
- Prima facie unconscionable.
- Never enforceable.
-
If a contract contains both a valid liquidated damages clause and an unenforceable penalty, what is the likely result?
- The entire clause is void.
- Only the penalty is struck; the valid liquidated damages remain.
- The party may elect either remedy.
- The non-breaching party recovers nothing.
Introduction
Liquidated damages and penalty clauses are common in contracts, but only valid liquidated damages are enforceable. Penalty clauses are not. The law also allows parties to limit remedies by contract, but such limitations may be subject to further restrictions, especially under the UCC. For the MBE, you must be comfortable spotting when an agreed sum is a valid substitute for proof of actual damages and when it is an unenforceable attempt to punish breach, and you must understand how far parties can go in restricting other remedies.
What Are Liquidated Damages and Penalties
A liquidated damages clause is an agreement by the parties, made at contract formation, to fix the amount of damages payable in the event of breach. A penalty clause is a provision that imposes an amount intended to punish the breaching party, rather than compensate for actual loss.
Key Term: Liquidated Damages
A contractually specified sum, agreed in advance, that is intended to be a reasonable estimate of the non-breaching party’s loss in the event of breach.Key Term: Liquidated Damages Clause
The contractual provision that sets out the liquidated damages amount and the circumstances under which it is payable.Key Term: Penalty Clause
A contract provision that sets a sum designed primarily to deter breach or punish the breaching party, rather than approximate anticipated or actual harm.Key Term: Penalty
An agreed damages amount that is unreasonably large or clearly punitive, and therefore unenforceable; ordinary damages rules apply instead.
Enforceability: Liquidated Damages vs. Penalties
Courts enforce liquidated damages clauses only if they are a reasonable estimate of anticipated or, under the UCC, sometimes actual harm. If the clause is intended to punish, or is grossly disproportionate to foreseeable loss, it is an unenforceable penalty.
The Legal Test for Enforceability (Common Law)
At common law, a liquidated damages clause is enforceable if both of the following are satisfied:
- Uncertainty of damages – Damages from breach are difficult to estimate at the time of contract formation; and
- Reasonable forecast – The amount is a reasonable forecast of just compensation for the harm caused by breach, judged at the time the contract is made.
If either element is missing, the clause is a penalty and unenforceable.
Key Term: Reasonable Forecast
An amount that reasonably approximates the expected loss from breach, based on information available when the parties contracted.
The UCC Variation
Under UCC §2-718(1), a liquidated damages clause in a contract for the sale of goods is valid only if the amount is reasonable in light of:
- The anticipated harm,
- The actual harm, or
- The difficulties of proof and inconvenience of otherwise obtaining an adequate remedy.
Unlike the traditional common-law test, the UCC allows a court to consider actual damages to validate a clause that might have been questionable at the outset, as long as it is not unreasonably large.
Worked Example 1.1
A contractor agrees to build a store for $200,000, completion due by June 1. The contract states, "If the contractor is late, he must pay $1,000 per day as liquidated damages." Actual damages for delay are uncertain but could be significant (lost sales, staff costs, advertising already purchased).
Answer:
The clause is likely enforceable. Delay damages are difficult to estimate in advance, and $1,000 per day is not obviously disproportionate to potential lost profits and carrying costs. It looks like a reasonable forecast, not a penalty.
When Is a Clause a Penalty
A clause is a penalty if:
- The amount is grossly excessive compared to anticipated loss.
- The clause applies to any breach, regardless of severity (e.g., minor technical breaches and catastrophic breaches alike).
- The clause is structured to deter breach (“to make sure you never breach”) rather than compensate loss.
If found to be a penalty, the clause is void and the non-breaching party may recover only actual damages proven under ordinary rules.
Worked Example 1.2
A software license states, "If licensee breaches any term, licensee must pay $500,000 as liquidated damages." The license fee is $10,000, and minor breaches (e.g., a single late payment or failing to give notice of a minor change) are possible.
Answer:
The clause is almost certainly a penalty. $500,000 is grossly disproportionate to any likely loss on a $10,000 contract, and the clause applies to all breaches, even trivial ones. It will not be enforced; the licensor must prove actual damages.
Mixed Clauses: Part Valid, Part Penalty
Sometimes a contract contains several agreed sums in the same provision—some reasonable, some not. Courts do not automatically strike the whole provision.
- If the valid part is severable from the penalty portion, courts will enforce the reasonable component and ignore only the penalty.
This is the logic behind question 3 in the Test Your Knowledge section.
Consequences of Characterization
-
If the clause is valid liquidated damages:
- The stated amount is the exclusive measure of damages for that breach (unless the contract clearly provides otherwise in a way consistent with compensation, not punishment).
- The non-breaching party need not prove actual damages, and cannot recover more, even if actual damages turn out to be greater.
- The breaching party generally cannot argue that actual loss was small or zero; they agreed to the pre-estimate.
-
If the clause is an unenforceable penalty:
- The clause is disregarded.
- The non-breaching party may sue for expectation damages under ordinary rules, plus incidental and foreseeable consequential damages, subject to mitigation and certainty.
- The fact that the parties wrote a penalty does not bar all recovery.
Worked Example 1.3
A seller and buyer agree that if buyer fails to close on a land purchase, the seller keeps the $20,000 deposit “as liquidated damages, which shall be seller’s sole remedy.” The price is $400,000. At the time of contracting, estimating seller’s resale prospects is difficult.
Buyer breaches; seller quickly resells for the same price.
Answer:
The clause is likely enforceable. Damages from a failed real estate sale can be hard to predict, and a 5% deposit is a common, reasonable pre-estimate of seller’s costs and risks. Seller keeps the $20,000 even though actual damages were small; seller cannot also seek additional damages, because the clause states this is the sole remedy.
Limitation of Remedies
Beyond agreed damages, parties may agree to limit the remedies available for breach—for example:
- Limiting the buyer’s remedy to repair or replacement of defective goods;
- Excluding recovery of consequential damages; or
- Capping total liability at a specified amount.
Key Term: Limitation of Remedies
A contract provision that restricts the remedies otherwise available for breach (e.g., “repair or replace only,” “no consequential damages,” or a monetary cap on liability).
At common law, such limitations are generally enforceable unless:
- They are unconscionable, or
- They contravene public policy (for example, attempting to disclaim liability for intentional torts).
The UCC supplies additional structure for contracts for the sale of goods.
UCC Article 2: Special Rules on Limitation of Remedies
UCC §2-719 allows parties substantial freedom to shape remedies, but imposes two important checks:
- Failure of essential purpose, and
- Unconscionability.
Key Term: Exclusive Remedy
A contractual remedy designated as the sole remedy (e.g., “Buyer’s exclusive remedy is repair or replacement of defective parts”).Key Term: Failure of Essential Purpose
Under UCC §2-719(2), a limited or exclusive remedy fails of its essential purpose when, in practice, it does not provide the buyer with the minimum adequate remedy the parties contemplated (for example, repeated failed repairs that never fix the defect).
Limited or Exclusive Remedy
Parties may restrict remedies to, for example, “repair or replacement of defective parts.” If parties clearly intend that remedy to be exclusive, the buyer ordinarily cannot seek other contract remedies unless the limited remedy fails of its essential purpose.
Examples of failure of essential purpose:
- Seller promises to repair defective machines but cannot fix them after repeated attempts.
- Replacement parts are unavailable, and buyer is left with unusable goods.
In such cases, the buyer is freed from the limitation and may recover the full range of UCC remedies, including incidental and consequential damages (unless a separate valid exclusion applies).
Exclusion of Consequential Damages
Key Term: Consequential Damages
Losses that do not flow directly from the breach in every case but arise from the non-breaching party’s particular circumstances (e.g., lost profits from a missed resale, lost production, or damage to other property).
UCC §2-719(3) distinguishes:
- Consequential damages for commercial loss – Limitations or exclusions are generally enforceable, unless unconscionable.
- Consequential damages for personal injury in consumer goods – An exclusion or limitation is prima facie unconscionable.
Key Term: Prima Facie Unconscionable
A clause that is presumed unconscionable unless the party seeking enforcement can rebut the presumption with evidence to the contrary.
So:
- In consumer goods cases, a clause saying “Seller is not liable for consequential damages for personal injury” is presumed invalid.
- In commercial sales, a clause excluding consequential damages for lost profits is normally valid, absent other unconscionability factors (e.g., extreme bargaining power abuse).
Worked Example 1.4
A contract for the sale of a refrigerator to a consumer states, "Seller's liability is limited to repair or replacement. Seller is not liable for consequential damages for personal injury." The refrigerator explodes, injuring the buyer.
Answer:
The exclusion of consequential damages for personal injury in a consumer-goods sale is prima facie unconscionable under UCC §2-719(3) and will not be enforced. The buyer may recover personal injury consequential damages despite the clause. The limitation to repair or replacement may also fail of its essential purpose if repair is impossible or inadequate.
Worked Example 1.5
A mining company contracted with a railroad to transport 10,000 tons of coal for $100,000. The railroad knew that the mining company had a resale contract where the price dropped $1 per ton for each day of delay. The transportation contract stated that the railroad “shall not be liable for any losses suffered as a result of late shipment.” The coal arrived 10 days late, and the mining company lost $100,000 in profits. It sues for those lost profits.
Answer:
The mining company is unlikely to succeed. The parties expressly agreed that the railroad would not be liable for losses due to late shipment—an exclusion of consequential damages (lost resale profits). Under the UCC, such an exclusion is generally enforceable in a commercial setting, absent unconscionability. The fact that the damages equal the entire contract price does not matter.
Unconscionability
Key Term: Unconscionability
A doctrine allowing a court to refuse to enforce a contract or clause that was excessively one-sided or oppressive at the time of contracting, considering both procedural (bargaining process) and substantive (harsh terms) factors.
Unconscionability may invalidate:
- A purported liquidated damages amount that is so high it effectively punishes breach.
- A limitation of remedies that leaves the buyer with no meaningful recourse, especially in consumer transactions.
Courts are more reluctant to find unconscionability in arms-length commercial contracts between sophisticated parties.
Exam Warning
Courts judge the reasonableness of a liquidated damages amount primarily at the time of contracting, not by looking back at how the breach turned out. Under the UCC, actual damages can be considered to support a clause, but a clause that was clearly punitive at the outset will not be saved just because actual damages later turned out to be high. Do not confuse this with the separate question whether the non-breaching party actually suffered a loss.
Common exam traps:
- Treating every clause labeled “liquidated damages” as valid. Labels do not control.
- Assuming a clause is invalid simply because actual damages were small or zero. What matters is the reasonableness of the forecast ex ante.
- Ignoring the special UCC rule that exclusions of personal injury consequential damages in consumer-goods contracts are presumptively unconscionable.
Revision Tip
If a clause is labeled "liquidated damages" but is grossly excessive or applies to trivial breaches, treat it as a penalty for MBE purposes. Then ask: what actual damages can the non-breaching party prove? Conversely, if damages are uncertain and the amount is modest and proportional, lean toward enforcing it.
Summary
- Liquidated damages clauses are enforceable only if (1) damages were difficult to estimate at the time of contracting and (2) the amount is a reasonable forecast of just compensation.
- The UCC allows courts to consider anticipated or actual harm and the difficulty of proof; the amount cannot be unreasonably large.
- Penalty clauses are void. If a clause is penal, courts disregard it and award actual expectation damages plus incidental and foreseeable consequential damages.
- Limitation of remedies clauses (e.g., “repair or replacement only,” or “no consequential damages”) are generally valid but may fail if unconscionable or, under the UCC, if they fail of their essential purpose.
- Under UCC §2-719(3), exclusions of consequential damages for personal injury in consumer goods are prima facie unconscionable, but exclusions for commercial loss are usually enforceable.
- Courts may sever an unenforceable penalty portion while enforcing a valid liquidated damages amount in the same provision.
Key Point Checklist
This article has covered the following key knowledge points:
- Liquidated damages are enforceable only when damages are hard to estimate at formation and the amount is a reasonable forecast of loss.
- A clause that is grossly disproportionate, applies to all breaches regardless of severity, or is obviously punitive is treated as a penalty and is unenforceable.
- If a liquidated damages clause is valid, the agreed amount normally becomes the exclusive measure of damages for that breach; the non-breaching party cannot recover more.
- If a clause is a penalty, it is struck down, but the non-breaching party may still recover actual expectation damages proven under ordinary rules.
- Limitation of remedies clauses (e.g., repair-or-replace, no consequential damages) are generally valid, but not if unconscionable or if they fail of their essential purpose (UCC §2-719(2)).
- Under the UCC, limitations or exclusions of consequential damages for commercial loss are usually enforceable; limitations of consequential damages for personal injury in consumer goods are prima facie unconscionable.
- Courts may strike only the penalty portion of a mixed clause, leaving a reasonable liquidated damages amount in place if it is severable.
- Labels (“liquidated damages” vs. “penalty”) are not controlling; the court looks to function and reasonableness.
Key Terms and Concepts
- Liquidated Damages
- Liquidated Damages Clause
- Penalty
- Penalty Clause
- Reasonable Forecast
- Limitation of Remedies
- Consequential Damages
- Unconscionability
- Exclusive Remedy
- Failure of Essential Purpose
- Prima Facie Unconscionable